Schedule Update – October 10, 2012

Asphalt Schedule
October 10, 2012

On Friday, October 12th Lakeside Industries will starting laying asphalt for the driveway aprons between the street and the sidewalk. They are scheduled to start at 7:30am and will be working through the end of the day.

Please note that the asphalt needs time to cool down so all driveways will be closed until the morning of Saturday, October 13th.

We ask that homeowners park on the shoulder starting Thursday night of October 11th.

Posted in Uncategorized

Weekly Schedule Update – September 27th

Concrete Schedule Update
September 27, 2012

Starting Monday, October 1st and going through Wednesday, October 3rd the concrete subcontractor will be working on the sidewalk from Holcomb Street to Sheridan Street.

  • Monday, October 1st  – Starting to prep and form the sidewalk
  • Tuesday, October 2nd  – Fine tuning of the forming of the sidewalk
  • Wednesday, October 3rd – Pouring the sidewalk
  • The morning of Friday, October 5th – Driveways will be open

We ask that homeowners park on the shoulder starting Monday morning the 1st of October.

If you should have any questions please contact Kara Rogers at 360-344-3064.

Posted in Uncategorized

Weekly Schedule Update – September 19th

Weekly Schedule Update
September 24th – September 28th 

Starting Monday, September 24th and going through Friday, September 28th the concrete subcontractor will be working on the sidewalk from Discovery Rd. to Holcomb St. We are asking homeowners in this area to please park their cars on the shoulder during this week. Please see the details below.

  • Monday, September 24th – Starting to prep the sidewalk
  • Tuesday, September 25th – Grading for the sidewalk
  • Wednesday, September 26th – Pouring the sidewalk
  • Thursday, September 27th & Friday, September 28th – Sidewalk will be drying
  • Friday, September 28th – Driveways will be open at the end of the day before the contractor leaves
Posted in Uncategorized

Hastings Avenue Sidewalk Project Update – September 14th

Please note that the concrete subcontractor will be forming and pouring sidewalk starting Monday (9/17) through Friday (9/21) starting at Discovery Rd. and moving up towards Holcomb St.

Posted in Uncategorized

Hastings Avenue Sidewalk Project Update – August 24, 2012

For the week of August 27th – August 31st the contractor, C & J Excavating will continue with the installation of the stormwater.

 

Posted in Uncategorized

Hastings Avenue Sidewalk Project Update – August 6, 2012

The City of Port Townsend went out to bid on the Hastings Avenue Sidewalk Project on May 30, 2012. We received five bids and they were opened on Thursday, June 21, 2012. The Project was awarded to C & J Excavating, Inc. of Carlsborg, WA as they were the lowest bidder.

The Hastings Avenue Sidewalk Project construction will start on August 15, 2012 with a contract of 45 working days for a completion date of October 16, 2012 or sooner. 

The City will update the project blog every Friday with information on what will be happening the following week once the project gets started.

For more information please contact:
Kara Rogers at (360) 344-3064
City of Port Townsend, Public Works Department

Posted in Uncategorized

Hastings Avenue Sidewalk Project – May 25, 2012 Update

The City of Port Townsend will be going out to bid on the Hastings Avenue Sidewalk Project Wednesday, May 30, 2012. Contractors bids will be due June 21, 2012 with construction scheduled to start July 23, 2012.

Posted in Uncategorized